Nevada Geothermal Power Inc. Provides Update on Blue Mountain Geothermal Power Project

Nevada Geothermal Power Inc. (NGP) (TSX VENTURE:NGP)(OTCBB:NGLPF) is pleased to provide the following update on Phase 1 development activities at its Blue Mountain, Faulkner I, 49.5 MW (gross) renewable energy geothermal power project.

A financing facility for the construction of the 49.5 MW Blue Mountain Faulkner I project in Nevada is expected to close shortly. NGP continues to maintain project timelines and terms with Ormat Technologies.

NGP has all the necessary permits for initial construction work, which is scheduled to commence in September 2008. NGP's wholly owned subsidiary, NGP Blue Mountain I LLC (NGP I), was issued a Limited Permit to Construct from the Public Utilities Commission of Nevada (PUC) at the Blue Mountain geothermal project on July 11, 2008. The grant of permit under the Utility Environmental Protection Act (UEPA) allows NGP I to grade the site and complete the foundations for the geothermal power plant.

Step-out Well 58-15, located 4,600 feet (1,402 meters) west of earlier production wells and originally planned for geothermal fluid re-injection, will be completed as a high-temperature production well. Production and injection tests conducted by GeothermEx indicate that Well 58-15 encountered reservoir fluid at 415 degrees F (213 degrees C), the highest temperatures yet measured at Blue Mountain, in a highly permeable zone at 5,600 feet (1,707 metres). The new production well location opens up the possibility of several fill-in production wells between Well 58-15 and other production wells already drilled by NGP.

The capacity of Well 58-15 flowing unassisted (unpumped) is estimated by GeothermEx at approximately 5.5 MW, net of parasitic power required for the power plant. Pumping was not considered by GeothermEx because of the higher temperature fluids. However, NGP is working with specialist consultants to assess the viability of pumping Well 58-15 utilizing line-shaft pumps equipped for high temperature service. If pumping proves feasible, Well 58-15 could produce approximately 10 MW (gross) or 7.5 MW (net) of power plant and pump loads.

During drilling, Well 58-15 identified shallow injection potential (the zone has been cased) in the interval between 1200 - 1600 feet (366 - 488 meters). The shallow permeable zone for injection contains much lower fluid temperatures and is separated from the deep production zone by a 3,000 foot thickness of impermeable rock. The shallow zone will be a primary target for future shallow injection wells to be drilled in the "West Injection Area".

The acid stimulation testing for Well 44-14 has been successfully completed. Well 44-14 will be re-entered and deepened to possibly tap the same deeper fault structure that was intersected in Well 58-14.

Injection Well 13-11 has been drilled to a depth of 7,162 feet (2,183 meters); however, the target fault was not found. A sidetrack well, or second leg, will be drilled at an angle to the west from below the casing shoe (2,025 feet, 617 meters) to intersect the projected target.

NGP has temporarily suspended drilling at Blue Mountain, having completed its equity contribution for the power project budget. The ThermaSource rig remains at the site, with drilling to resume in September. NGP is on track to complete the project, including resource drilling, transmission line installation, and pipeline and power plant construction by December 31, 2009.

About Nevada Geothermal Power Inc.: Nevada Geothermal Power Inc. is a renewable energy company developing geothermal projects in the United States to provide electrical energy that is clean, efficient and sustainable. NGP is committed to the geothermal industry and currently owns a 100% leasehold interest in four properties: Blue Mountain, Pumpernickel, Black Warrior, all located in Nevada and Crump Geyser in Oregon. These properties are at different levels of exploration and development. NGP estimates a potential of approximately 150 MW to over 200 MW from the current leaseholds.

Nevada Geothermal Power Inc.

Brian D. Fairbank, P. Eng., President & CEO

This Press Release contains certain forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. We have tried, whenever possible, to identify these forward-looking statements using words such as "anticipates", "believes", "estimates", "expects", "plans", "intends", "potential", and similar expressions. These statements reflect our current belief and are based upon currently available information. Accordingly, such forward-looking statements involve known and unknown risks, uncertainties and other factors which could cause the Company's actual results, performance or achievements to differ materially from those expressed in or implied by such statements. We undertake no obligation to update or advise in the event of any change, addition, or alteration to the information catered in this Press Release including such forward-looking statements.

SOURCE: Nevada Geothermal Power Inc.

Nevada Geothermal Power Inc.
Shelley Kirk
Investor Inquiries
(604) 638-8784 or Toll Free: 1-866-688-0808 X118
Website: www.nevadageothermal.com
Pro-Edge Consultants Inc.
Tracy Weslosky or Fred Cowans
Managing Partners
(416) 581-0177 or Toll Free: 1-866-544-9622
Email: info@pro-edge.com
Website: www.pro-edge.com

Copyright (C) 2008 CCNMatthews. All rights reserved

News Provided by COMTEX


Related terms: budget, ceo, construction, electrical, energy, equity, exploration, geothermal, nevada, oregon, pipeline, plant, power plant, president, renewable energy, securities, technology, track, utilities

Sponsored Links

 

Related Articles

Nevada Geothermal Power Inc. Corporate Update - Zibb.com
Sep 30, 2008
Nevada Geothermal Power Inc. Corporate Update Nevada Geothermal Power Inc. (NGP) (TSX VENTURE...contractor for the power plant. NGP does not expect...geothermal power plant at Blue Mountain as a result of recent...

BRIEF: Eilat hotels to get power from Aqaba private plant: The private power plant will not be hooked up to the Jordanian power grid, but will only supply electricity to Israeli consumers.
Sep 10, 2008
BRIEF: Eilat hotels to get power from Aqaba private plant: The private power plant will not be hooked up to the Jordanian power grid, but will only supply electricity to Israeli consumers. News from LexisNexis...

--> Glitnir Bank Advises Nevada Geothermal Power On Financing For Blue Mountain Geothermal Power Plant
Sep 9, 2008
Headline functionality has been disabled from your intranet. Please contact your system administrator to report this fault. If you are the system administrator, please click here.

Running the Plows
Sep 22, 2008
...clutch pump to run the plow and another power plant for the back-of-the-truck functions...possible to use a simple centralized power plant that can run all the hydraulic functions...2,000-psi centralized hydraulic power plant. “Conventional solutions couldn't...